24 September 2009 – undertaking of works at the construction site and erection of first modular units
![]() |
![]() |
![]() |
30 September 2009 – placement of central heating pipes and electricity cables
![]() |
![]() |
08 October 2009 – wooden roof framework assembly
![]() |
![]() |
![]() |
11 October 2009 – laying of PVC lining, finishing of the roof, wooden projecting roof erection
![]() |
![]() |
![]() |
![]() |
22 October 2009 – sanitary ceramics assembly and conclusion of other contractual works
![]() |
![]() |
![]() |
29 October 2009 – conclusion of all contractual works
![]() |
![]() |
![]() |